What are we waiting for?
Michael Riley sent me an update on where the materials/ equipment on order for Zeke's are at, so I thought inquiring minds would want to know:
Steel is shipping late next week. Date not firm yet.
Dan Bruce and I are on the same page for the bathrooms. In the process of getting things lined up.
Lighting Rig, about 80% of it is on order. I'm still working on finializing the remainder equipment order.
Sound System - waiting for update on our order.
Tectum - waiting for update on our order.
Doors - met with Doors Inc today and Dan B. 5 weeks from order on wood. So probably 6-7 weeks before they are here depending upon how fast they get back to us with the new quote and we can nail down any remaining issues. Frames for café will be here within a week, but won't get installed until Dan's ready for the bathrooms.
Window Shades - electrical parts on order as of this upcoming Monday. Probably another 4-6 weeks after that, installation will be complete.